Solar Farm Update March 2016

The Phase 1 site has energised and is now exporting electricity to the grid, meeting the connection date by a comfortable margin. The majority of major construction work is now complete. The construction compound will be moved in the coming weeks, leaving a small presence for testing purposes. The planting of the wild flower meadow will take place in the next planting season which will likely be in the spring, however this depends on weather conditions over the next few months.